TTMC II Methanol Plant

Industrie:
Petrochemical Industry
Land:

Quality in record time: a methanol plant in Trinidad

Um diesen Inhalt sehen zu können, benötigen Sie das kostenlose Flash-Plugin... hier geht es zum Download

Setting a new record, Ferrostaal handed over the methanol plant ready for commissioning after the construction period of only 22 months to the customer Trinidad and Tobago Methanol Company (TTMC). To guarantee the financing of this project, Ferrostaal together with the Trinidadian government became shareholder in TTMC.

As the general contractor, Ferrostaal was responsible for the coordination of the entire project. The engineering could be realized on the basis of the previous CMC design by adapting the complex to a higher production capacity. Procurement and Construction have been prepared thoroughly, so that a “fast track schedule” enabled a parallel implementation of all disciplines.  Due to efficient and high-quality local performance, the methanol complex could start production eight months earlier than envisaged. Since February 1996, TTMC II produces 1,650 tonnes of methanol per day.

Overview

Type of Contract

EPC / LSTK

Client 

Trinidad and Tobago Methanol Company (TTMC)

Project

TTMC II Methanol Plant

Plant capacity

1,650 MTPD / 550,000 MTPY

Plant site

Point Lisas Industrial Estate

Partners

JM (Technology and Engineering), ICI (Technology and Engineering), Proman (Construction)

Turnkey handover

1996

 

 

Beliebte Themen

Solarenergie   Ölförderung   Ingenieur Jobs  Projektmanagement   GuD-Kraftwerk  Kombikraftwerk   Solarthermische Kraftwerke  Recyclinanlage  Methanolanlage Ammoniakanlage  Gasförderung Petrochemische Anlagen  Verpackungsmaschinen Engineering Procurement Construction  Druckmaschinen Plastikmaschinen Automobil Dienstleistungen  Parabolrinnenkraftwerk Melaminanlage Equipment Solutions